    Hi Everyone

    I am contract stage for a granny flat we are having built in NSW.

    The builder has included a couple of things I would like to push back on. Any recent experience from people who have built granny flats in NSW would be appreciated.

    1. Delay damages $1 per working day (that’s cheap for him but expensive for us, the loan still has to be paid)
    2. 15% interest payable by us for any late payments to the builder (the bank is financing the build so this could be expensive for us too)
    3. Draw down schedule – how do we get this to be one that the bank will be agreeable with.

    Our legal rep had a look at the contract but he is not used to construction loans.

    Looking forward to hearing about your experiences and knowledge.

    Many thanks

    ronnie

    Profile photo of TerrywTerryw
    Participant
    @terryw
    Join Date: 2001
    Post Count: 16,213

    Best to get a lawyer who can advise on building contracts.

    Terryw | Structuring Lawyers Pty Ltd / Loan Structuring Pty Ltd
    http://www.Structuring.com.au
    Email Me

    Lawyer, Mortgage Broker and Tax Advisor (Sydney based but advising Aust wide) http://www.Structuring.com.au