All Topics / Help Needed! / 18 Months To Build Two Townhouses

Viewing 3 posts - 1 through 3 (of 3 total)
  • Profile photo of ladybirdladybird
    Participant
    @ladybird
    Join Date: 2003
    Post Count: 61

    I have had an initial consultation with a turnkey development company on building two side-by-side 2-Storey Townhouses at the rear of my property. He gave an estimate of 18 months to complete the project following planning approval being obtained.

    Is this reasonable for Perth?

    Profile photo of Scott No MatesScott No Mates
    Participant
    @scott-no-mates
    Join Date: 2005
    Post Count: 3,856

    It sounds like 8-10 months too long unless it is a difficult site (sloping, heavily treed, poor ground conditions, alot of siteworks prior to commencement, very complex design etc).

    Profile photo of LockymacLockymac
    Member
    @lockymac
    Join Date: 2009
    Post Count: 78

    Much to long we are doing alot of developments in Perth at the moment and twelve months is the worst quote we have got back. It sounds like your company has enough work already might be a better idea to shop around. Might cost you a little more but shave six months of the job??

    Cheers