  • Profile photo of LinarLinar
    Member
    @linar
    Join Date: 2004
    Post Count: 567

    I am currently in the process of building three houses on the one (community titled) site.  What is an acceptable build time for a project like this?

    All houses are pretty much identical, with three bedrooms, two way bathrooms and very basic landscaping.

    Cheers

    K

    Profile photo of Scott No MatesScott No Mates
    Participant
    @scott-no-mates
    Join Date: 2005
    Post Count: 3,856

    I'd be expecting 9-12 months depending upon the complexity of the project, the quality of the project manager/builder, issues in the ground, extent of consultant involvement (design), adequate funding for variations/contingencies, weather etc.

    Profile photo of hleunghleung
    Participant
    @hleung
    Join Date: 2007
    Post Count: 141

    I agree with Scott No Mates.  9 – 12 months is about average.

    Profile photo of LinarLinar
    Member
    @linar
    Join Date: 2004
    Post Count: 567

    So for a relatively straightforward project, ie, no ground issues, no design issues, no funding issues etc, would 6 months from the laying of the slab to handover be considered a good turnaround time?

    K

    Profile photo of hleunghleung
    Participant
    @hleung
    Join Date: 2007
    Post Count: 141

    I've built quite a few properties and something always crops up which delays the project ie rain, getting the right tradesmen at the right time, materials such as kitchen appliances not available.  6 months is possible if everything falls into place.

    I know it's extreme but I've got a mate who has still hasn't got his project finished after 24 months.  His builder is not going to go bust, just lots of issues.