    hi, I have remove my old kitchen and plan to put in new kitchen, new floorboard, new plaster wall/ceiling and paint it. What's the right sequence of doing this?

    Currently kitchen is gone and floor/ceiling has holes and gap every where. I am thinking of getting floor/ceiling plaster up, painted, then floor board, then only kitchen going in.. or should I leave floor board after kitchen put in? current floor is solid timber but with holes and gap.

    Profile photo of give90give90
    Member
    @give90
    Join Date: 2007
    Post Count: 54

    ……I am thinking of getting floor/ceiling plaster up, painted, then floor board, then only kitchen going in..

    you've got it about right. do all the electrical and plumbing first though while there are still holes to thread into and the cupboards are out of the way.