  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 3 months ago

    Ahhhh, so much can get done with sunny weather

    All windows are now installed and the dwellings will be wrapped tomorrow as a result. The shaftliner is in too – between the party wall for the rear units. This is to protect from fire. Some use double brick instead but i have found this way to save on space making the units more spacious and…[Read more]

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 3 months ago

    Been busy lately to update lately. I have attached a few photo's. The roof truss for the single level units are complete along with the posi truss for the townhouses.

    The fascia and gutter is up for the single level units too. Weather has really delayed work – very hard to put the roof truss in wet weather.

    Oscar<img alt="" border="0"…[Read more]

  • oc1 replied to the topic Property Cycle in Melbourne in the forum Help Needed! 11 years, 3 months ago

    Prices are rising but they haven't peaked. Not all suburbs have risen either. You should be ok as long as you don't pay too much. The level of stock is also low at the moment which is putting upward pressure on prices.

    Oscar

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 3 months ago

    A few more pics. Garages pretty much done (will be completely finished when the bricklayer is back in 2 weeks) with the T bars put in. All ground level frames are completed too. You will see the steel beams in one of the units too.

    Moving forward the single level units will have the ruff truss and windows installed. Weather is a problem…[Read more]

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 3 months ago

    Hi guys

    Frames are up now for the back two units. The bricklayer has been there this week as well putting up the garages. The roof truss comes tomorrow for the rear units. All going along well. By the end of next week i should be close to having all frames completed and roof truss for all units completed.

    Cheers
    Oscar<img alt="" border="0"…[Read more]

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 4 months ago

    Full steam ahead from here. The chippie has commenced after waiting for the concrete to cure. Photo's show the bottom plates on a couple of the units and the remaining units have been marked out. This was we can order the roof truss for late next week.

    The bricky also starts on Monday with the garages. smiley

    Oscar<img alt="" border="0" height="496"…[Read more]

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 4 months ago

    Correct, to the back of the block. Works out really well as we tap into the existing pipe.

  • oc1 replied to the topic financial advisor in melb in the forum Help Needed! 11 years, 4 months ago

    Maybe try Terryw here from the forum as a start. He really knows his stuff!

    Oscar

  • oc1 replied to the topic Draughtsman in Frankston in the forum Hi Landt64 11 years, 4 months ago

    Hi Landt64

    I'd say your best would be to hit the streets or the Yellow Pages. Just remember the same planning code (Rescode) applies to each council in Victoria. In effect everyone plays by the same rules. Each council will have their unique requirements or interpretations which isn't a huge barrier to overcome.

    Oscar

  • oc1 replied to the topic 3 unit development in Epping VIC in the forum Value Adding 11 years, 4 months ago

    Well, the units are now completed. The last coat (colour) of the render gets applied today. Time to sell now. I'll put some pics up tomorrow.

    Subdivision wise, I received the Statement of Compliance from council on Monday and my surveyor has lodged all paperwork to the Land Registry Office. I'm waiting on mortgage consent to complete the process.…[Read more]

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 4 months ago

    Some photo's attached of the concrete slabs, both during and after. A very good job by the concretor. Over the weekend we had a lot of rain making the site muddy. I have the excavator there cleaning out the mud and excess soil and placing crush rock throughout. This should be enough to avoid going in knee deep surprise

    Oscar<img alt="" border="0"…[Read more]

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 4 months ago

    Hi Urilla

    The price includes everything and at the quality of finish you have mentioned. The cost per m2 ranges and I do an estimate for each project. There's too many variables. Stormwater and services etc. As a guide though I would use $1500m2 for a medium finish. My costs are lower as I am a registered builder too.

    The other important aspect…[Read more]

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 4 months ago

    Hi guys

    I thought I would put up a few pics showing the various stages before the concrete is poured. Weather permitting this will occur tomorrow. I'll then wait a few days for this to settle as proper curing will greatly increase concrete strength and durability. My carpenter will then come onto site to begin construction of the frames. smiley

    Oscar…[Read more]

  • oc1 replied to the topic 3 unit development in Epping VIC in the forum Value Adding 11 years, 4 months ago

    Floorboards will be completed today. I have attached a photo from yesterday. They are bamboo floors.
    Also, the landscaping has moved along. All coming together now. I'm now looking forward to having it cleaned over the weekend. smiley

    <img alt="" border="0" height="496" id="lightboximg13"…[Read more]

  • oc1 replied to the topic Amendments to the residential zones in Victoria in the forum Value Adding 11 years, 4 months ago

    Be careful of properties which have a heritage overlay. Chances are you will have an 8m height restriction. Will make apartments (3 level) a little difficult.

    Oscar

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 4 months ago

    Update

    Earlier in the week the plumbers were out there for 2 days completing the below ground sewer. They partially completed the stormwater too, mainly behind the rear units.

    Tomorrow the concreter begins. Forecast for rain tomorrow but the rest of the week should be nice and sunny

    Cheers
    Oscar

    <img alt="" border="0" height="496"…[Read more]

  • oc1 replied to the topic 3 unit development in Epping VIC in the forum Crossovers and car spaces 11 years, 4 months ago

    Crossovers and car spaces have been poured now. It cleans up the site tremendously! I had a massive clean inside the units so that the floorboards and carpet could be laid (lots of mud from all the wet weather). The carpets are in and the bamboo flooring goes in tomorrow. The brick piers have been rendered too – just waiting for a sunny day for…[Read more]

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 4 months ago

    Nope, never had. No reason why you can't though. A mate of mine who's building at the moment has included a washing machine on his current build. Can't say it's made a difference or not. I'd rather spend that money on landscaping.

    Oscar

  • oc1 replied to the topic Foot into Development in the forum Value Adding 11 years, 4 months ago

    Good work!
    I wouldn't say it's the BEST way, it is A way to profit from development.

    Oscar

  • oc1 replied to the topic My latest development – 4 dwellings in Melbourne in the forum Value Adding 11 years, 4 months ago

    wilko1 wrote:
    Hi Oscar

    What's the block dimensions looks like over 1400 sqm ?
    How did you buy the site, on the market or off the market?
    What were some of your negotiating strategies to get your long settlement?
    Planning to sell 3 keep 1 ?

    Thought i would continue on from your developing 101 post. Good information for people to read.
    cheers…[Read more]

  • Load More

oc1

Step 1 - 0% Complete

Fill Out Your Member Profile Below

Fill in the required fields below to complete your registration.

Registration not only grants you full access to this website, but will also enable us to send you our newsletter, latest investor tips, strategies and information about events/products relevant to investors. You can opt out at any time.

Used to log in to the website and for targeting with messages. Alphanumeric characters only. No spaces allowed..

Member Login
Lost your password?
×
159,207

Register Free To Unlock Unrestricted Access To PropertyInvesting.com

×
1-Day Millionaire Mastermind Workshop - Only LIVE Training in 2019!